Availability
One of the pillars of successful project management is the notion of a critical path. To understand what this is, you need to ask yourself: 'What ultimately determines the duration of my project?'
The answer is: the critical path.
The critical path is a series of activities that set the definite end date of the project. The date is definite because the activities (called critical activities) have no slack. Having no slack is the definitive feature of a critical activity. As a result, you will want to pay special attention to critical activities as delaying even one of them may have an adverse 'domino effect' on the whole project.
Birdview calculates the critical path as follows:
- An activity with the latest end date is located.
- Moving backward, a chain that includes all dependent activities and parent ones is built starting from the latest end date activity
Note
An activity stops being critical when it has no planned end date and actual completion date, because it then can no longer affect the completion of successor tasks or the project finish date.
Where can critical path/critical activities be viewed in Birdview?
Critical path activities can be viewed on the Gantt tab of the Activity center when the option "Critical path" is enabled in the "Show" menu.
Such activities are colored red.
How do you shorten the critical path?
If you want to bring in the project end date, you need to bring in the dates of your critical path activities. To do this, you can:
- Shorten the duration or work on an activity on the critical path,
- Break a critical task into smaller activities that can be worked on simultaneously by different resources,
- Set the lead time between dependent activities where applicable,
- Revise activity dependencies to allow more scheduling flexibility,
- Schedule overtime, or
- Assign additional resources to work on critical path activities.
Note
If you bring in the dates of your critical path, a different series of activities could become the new critical path.
Note
If you bring in the finish dates of the critical path and another series of activities does not overtake it, then you can successfully bring in the finish date of the project as a whole.