Availability
Overview
There are cases when you close the last subactivity under an activity or last activity under a project. Naturally, what you'd expect is that the activity or the project will be closed, too. Two possible scenarios are discussed below.
In this article
Changing status to Close
When you try to save an activity after having changed its status to Closed (or any equivalent, see Activity statuses: treat as completed or not), you may get a message as follows:
Choosing OK will result in the parent activity’s status being changed to "Closed".
The same applies to the status of the last open activity under a project being changed to Closed. The project will be marked as completed after choosing "OK".
Changing progress to 100 percent
If you change an activity’s progress to 100 percent, you will receive the following message:
You have specified that this activity is 100% complete. Do you want to complete this activity? Press "OK" to change the status.
Choosing "OK" will have the activity to be marked as completed.