Availability
Overview
This article answers the most common questions about the out-of-the-box (OOTB) Power BI reports in Birdview: where the numbers come from, how the less obvious indicators are calculated, and why slicers and filters behave the way they do. Use it together with the help icons and tooltips outside each report.
In this article
Permissions
To open the reports, a user needs an access level with the Access to BI Dashboards option enabled. An administrator can also limit individual reports to specific access levels.
Out-of-the-box reports at a glance
The out-of-the-box set has 17 reports in four groups. Fourteen are Live; the three resource and labor reports are Refresh (see Where the data comes from).
| Report | Group | What it shows | Mode |
|---|---|---|---|
| Internal Project Status | Portfolios and projects | Status of all projects: KPI strip, projects by status, delivery timeline by month, table with health, SPI, CPI and the latest comment | Live |
| Client Project Status | Portfolios and projects | One project: manager, progress, health, latest comment; milestones with due date, status and progress | Live |
| Portfolio & Project Health | Portfolios and projects | Portfolio health: projects by status, health and manager, activities by deadline; drill-through to Project Health with milestones and an activity calendar | Live |
| Project Score Card | Portfolios and projects | One project: progress and hours, profitability, Schedule / Budget / Finance panels, actuals vs EAC; a separate page for projects without billing | Live |
| Baseline vs Actual | Portfolios and projects | Baseline vs current dates: schedule KPIs, Current / Baseline Gantt, variance and schedule state per activity | Live |
| Risk Assessment | Portfolios and projects | Project health and trouble indicators across the portfolio, financial indicators vs targets; drill-through to Project Risk Assessment; a separate page for companies without billing | Live |
| Actual and Forecasted Cost vs. Budget | Finances | Budget, actual cost and EAC cost per project, with variances | Live |
| Burndown Labour Report | Finances | Labor budget consumed month by month, actual and planned | Refresh |
| Burndown Expense Report | Finances | Planned vs actual expenses month by month, remaining expense budget | Live |
| Finances Overview | Finances | One project: billed vs actual cost, payments, margin, actuals vs EAC, payment and expense details | Live |
| Invoicing Report | Finances | Invoiced, paid, overdue and not-due amounts; Summary, Details and Aging pages | Live |
| Profit Forecast | Finances | Expected profit vs target by month and fiscal quarter of the projects' end dates | Live |
| Billings and Cost (Monthly) | Finances | Billings per month, billable / non-billable hours, cost and revenue analysis; Billing Overview page | Live |
| Time Logs | Time Logs | Logged time by customer, space, portfolio, project or person, with a detailed table | Live |
| Billable vs. Non-billable (Weekly) | Time Logs | Weekly share of billable hours against a target | Live |
| Utilization Reports | Resources (Workload) | Utilization, Hours and Capacity pages: scheduled and logged work vs capacity; non-billable variants | Refresh |
| Planning Reports | Resources (Allocations) | Utilization, Hours and Capacity pages based on hard and soft allocations | Refresh |
Note
Out-of-the-box reports use standard Birdview fields only. Reports built on custom fields or a company's own workflows are Custom reports and are estimated separately.
Where the data comes from
The reports read your Birdview data directly: the same projects, activities, time logs, expenses, payments and invoices you see in the application. Nothing is entered or stored separately in Power BI.
Calculated values come from Birdview
The reports reuse values that Birdview has already calculated, so they match what you see in the application:
- Estimated hours, Actual hours and Hours left of a parent activity include all its sub-activities, the same as in the Activity center grid.
- Budget, EAC, ETC and profit are the values from the project's financials.
- Project health, SPI and CPI are taken from Birdview as they are; Power BI does not recalculate them.
Live and Refresh reports
Each report is labeled Live or Refresh.
| Live | Refresh | |
|---|---|---|
| How data is read | Directly from the database each time you interact | From a snapshot loaded on a schedule |
| Freshness | Near real time | As of the last scheduled refresh, in your company's time zone |
| Speed | Each click recalculates the page | Fast, because it works on the snapshot |
| How to tell | — | Last Refresh badge in the report header |
A report is made Refresh when its calculations are too heavy to run on every click, as with capacity and utilization.
Tip
If a Refresh report does not show a change you just made in Birdview, check the Last Refresh time first. The change will appear after the next scheduled refresh.
Which items are included
- Projects that are archived, in a draft status or marked as templates are excluded from all reports.
- Deleted projects, activities and time logs are removed from Birdview and disappear from the reports as well.
- Some reports look at a fixed time window, counted from today:
| Report | Window |
|---|---|
| Risk Assessment, Portfolio & Project Health | Open projects, plus completed projects that started on or after January 1 of the previous year |
| Utilization Reports | From 6 months back to 12 months ahead |
| Planning Reports | From 12 months back to the end of the current year |
Who sees what
Reports do not apply project-level permissions: anyone who can open a report sees the data of all projects in the account. Control who opens each report with the Access to BI Dashboards option and report restrictions by access level.
Project health, SPI and CPI
Health in the reports is the same value you see in Birdview; Power BI only displays it. It is based on two earned-value indices compared to a threshold, which is 1 by default.
- SPI (schedule performance index) shows whether progress keeps pace with the time that has passed. SPI above 1 means ahead of schedule.
- CPI (cost performance index) shows whether the work done is worth the hours spent. CPI above 1 means less effort than planned.
See Project health.
Health values
| Health | Color | When |
|---|---|---|
| On Track | Green | Both indices are at or above the threshold, or one is good and the other is not available |
| At Risk | Yellow | One index is below the threshold, the other is above it or not available |
| Action Required | Red | Both indices are below the threshold, or one of them is "definitely bad" |
| Not Calculated | Gray | The project has not started yet or is in a status treated as completed |
An index is "definitely bad" in two cases:
- SPI: the project's end date is in the past.
- CPI: actual hours exceed estimated hours and hours left are 0.
Tip
If most projects in a report show Action Required, check their end dates first. An end date in the past is the most common reason.
What changes health
Health cannot be set manually; it changes when the data behind it changes.
| Change in Birdview | Affects | Effect |
|---|---|---|
| Move the project end date into the future | SPI | Removes the "end date in the past" condition |
| Update the progress (% done) of activities | SPI and CPI | Progress is compared with elapsed time and with hours spent |
| Update estimated hours or hours left | CPI | Recalculates the planned effort the hours spent are compared with |
Notes
- Project health is calculated independently of activity health. A project can be On Track while some of its activities are red.
- The threshold is set by an administrator. With Allow calculating CPI and SPI individually (Company settings > Advanced settings > Project health settings), one index is calculated even when the other is unavailable.
- A project with zero actual hours has no CPI. Reports show an unavailable index as n/a.
- Health may take a moment to recalculate after a change.
Risk Assessment
Risk Assessment shows which projects are in trouble and why: Birdview project health plus eight trouble indicators checked for every project. For how indicators work in Birdview, see Trouble and problem indicators; for the financial values, see Project financials.
Trouble indicators
| Indicator | A project has it when |
|---|---|
| End Date | The project end date is in the past |
| Estimated Hours | Actual hours exceed estimated hours |
| Total Budget | EAC cost exceeds the budget |
| Total Revenue | EAC billable is below the target revenue |
| Budget Variance | Budget variance is negative |
| Revenue Variance | Revenue variance is negative |
| Profit Variance | Profit variance is negative |
| Target Profit | Expected profit is below the target profit |
Notes:
- Select one or more indicators in the indicator slicer to keep only projects that have at least one of them.
- In the project table, each triggered indicator is colored by the project's health.
- The W/O Billable page is for companies that do not use billing; it leaves out revenue and profit.
Project Risk Assessment
Right-click a project and select Drill through > Project Risk Assessment to see its health, SPI, CPI, hours used, an activity Gantt and the activity list.
| Counter | Activities counted |
|---|---|
| Overdue | Open, with the end date in the past |
| Due in 3 days | Open, due within the next 3 working days |
| Late | Closed after their end date |
| Over budget | Estimated labor cost exceeds the activity budget |
Notes:
- Days are counted in working days.
- The Hours used meter is actual hours divided by estimated hours: yellow from 80%, red above 100%.
Baseline vs Actual
The report compares each activity's current dates with its baseline: the planned dates saved when a baseline was captured in Birdview.
Which current date is used
| Activity | Current end date in the report |
|---|---|
| Closed (status treated as completed) | Actual completion date |
| Open, planned end date in the past | Today: the activity cannot finish earlier than today |
| Open, planned end date today or later | Planned end date |
Variance is counted in calendar days.
Example:
Baseline end: March 10. The activity is still open, its planned end date is March 12, and today is March 20. The current end date is March 20, so the variance is +10 days, not +2.
Schedule state
Each activity gets one state, checked in this order:
| State | When |
|---|---|
| Completed late | Closed, and the current end date is after the baseline end |
| Completed | Closed on or before the baseline end |
| Overdue | Open, with the planned end date in the past |
| Finishing late | Open, planned end date after the baseline end |
| No baseline | No baseline captured |
| On plan | Everything else |
Notes:
- Activities without a start date are not shown.
- Activities without a captured baseline have no variance.
- Capturing a new baseline replaces the old dates, so all variances start again from zero.
Financial reports
Financial reports use the budget, cost, EAC, billing and profit values from the project's financials in Birdview. For what each value means and how it is calculated, see Project financials.
Actual and Forecasted Cost vs. Budget
| Variance | Formula | Negative means |
|---|---|---|
| Forecasted | Budget − EAC cost | The project is expected to finish over budget |
| Actual | Budget − actual cost | The project is already over budget |
Use Show Variance As to switch the chart and KPIs between the two. Projects without a budget are not counted as over budget.
Burndown reports
| Burndown Labour Report | Burndown Expense Report1 | |
|---|---|---|
| Budget | Project budget | Total of the project's planned expenses |
| Past months | Internal cost of logged time | Actual expenses |
| Future months | Scheduled hours × the person's internal hourly rate | — |
| Remaining | Budget − cumulative cost to the month | Budget − cumulative actual expenses to the month |
|
1
The Expense report shows the months between the project's
start and end dates.
| ||
Finances Overview
The report shows one project at a time: what was billed and received against its actual cost.
| KPI | Formula | Green | Yellow |
|---|---|---|---|
| Profit margin | Profit ÷ billed | 30% and above | 15–30% |
| Payment coverage | Received payments ÷ actual cost | 100% and above | 80–100% |
| Collected | Received payments ÷ billed | — | — |
Invoicing Report
Invoices in Draft or Void status are excluded. The remaining invoices get a due status based on today's date.
| Invoice status | Today vs due date | Due status |
|---|---|---|
| Invoiced | After the due date | Overdue |
| Invoiced | On or before the due date | Not due yet |
| Paid | — | Paid |
Notes:
- Unpaid = Overdue + Not due yet.
- Collected = paid ÷ invoiced: green from 80%, yellow from 50%.
- Aging is the number of days past the due date, grouped as Current, 1–30, 31–60, 61–90 and 91 days and over. The Aging page shows invoices in Invoiced status only.
- Terms are shown as Due upon receipt or Net N, where N is the number of calendar days.
- Uninvoiced work on the Details page is billable time, flat fee activities and billable actual expenses not yet added to an invoice. Its share of all billable work turns yellow from 15% and red from 30%.
Profit Forecast
Each project's expected profit is placed in the month and fiscal quarter of the project's planned end date; it is not spread over the project's duration.
| Value | Formula |
|---|---|
| Expected profit % | Expected profit ÷ EAC billable |
| Target profit $ | EAC billable × target profit % |
| Weighted average % | Total expected profit ÷ total EAC billable |
Note
The fiscal year starts on June 1 and is named after the year it ends in: June 2026 – May 2027 is FY2027, and Q1 is June–August.
Billings and Cost (Monthly)
These reports are:
- Total billings per month = billable time logs plus flat fee activities, placed in the month they were logged or completed.
- Cost Analysis shows each person's billable and non-billable hours, internal cost, rate and billing.
- Revenue Analysis compares each project's total PO amount (target revenue) with spending to date: Remaining = PO amount − spending.
Time logs, capacity and utilization
Time reports count the hours logged in Birdview; resource reports compare scheduled, allocated or logged work with each person's capacity. Weeks start on Monday in all of them.
Time logs
- Every time log belongs to an activity; the report finds the project through that activity.
- In Time Logs, use Time Logged By to group hours by customer, space, portfolio, project or person.
Billable vs. Non-billable (Weekly)
| Setting or value | Meaning |
|---|---|
| Billable % | Billable hours ÷ all logged hours of the week |
| Target Billable % | Target line, 70% by default, adjustable from 70% to 100% |
| Minimal week hours | A person's billable % is shown only if they logged at least this many hours that week; 8 by default |
| Logging coverage | People who logged time ÷ people assigned to activities in the selection |
Note
Billable % is green when at or above the target, yellow up to 5 percentage points below it, and red below that.
Capacity
Capacity is the number of hours a person can work on a given day. Only Monday to Friday count.
| Day | Capacity |
|---|---|
| Regular working day | Hours from the person's working schedule for that weekday |
| Full-day vacation | 0 |
| Half-day vacation | Half of the scheduled hours |
| Public holiday | 0, even if a vacation was also entered for that day |
Notes:
- A public holiday applies to a person when it has no region, or when its region matches the person's country (and state, if set). People without a country get only holidays with no region.
- Only active people with a working schedule are included. People without a job role appear under No Job Role.
- Unnamed resources get the company's default hours per day, only on the days they are allocated, and holidays with no region only.
Example:
A person works 8 hours a day, Monday to Friday. In a week with one public holiday and one half-day vacation, capacity is 5 × 8 − 8 − 4 = 28 hours.
Utilization
| Report | Selector | Utilization = |
|---|---|---|
| Utilization Reports | Scheduled | Estimated Hours in Workload ÷ capacity |
| Utilization Reports | Actual | Hours logged ÷ capacity |
| Planning Reports | Hard Allocations | Hard-allocated hours ÷ capacity |
| Planning Reports | Total | Hard + soft allocated hours ÷ capacity |
Notes:
- Utilization Reports also show billable utilization: only billable work ÷ capacity. The non-billable pages show the rest.
- Availability = capacity − scheduled or allocated hours.
- Colors: below 80% underused, 80–100% healthy, above 100% overbooked.
Tip
In the example above, 35 scheduled hours against 28 hours of capacity give 125% utilization: the person is overbooked that week.
Slicers and filters
In single-project reports — Client Project Status, Project Score Card and Finances Overview — only the Project slicer filters the page. The Space, Portfolio and Customer slicers only narrow the list of projects you can pick from.
Slicer flow in single-project reports
Every visual on these pages describes one project: its health, progress, milestones and financials. Combining several projects would give numbers that mean nothing, such as summed progress, so the page always follows the project you select.
Selecting a project does not narrow the other slicers, so you can switch to another space or portfolio at any time.
Selecting a project
The workflow is as follows:
- Select a value in a higher-level slicer, for example Portfolio.
- Open the Project slicer: it now lists only the matching projects.
- Select a project. All visuals on the page update.
Tip
After changing a higher-level slicer, check that the project you want is selected in the Project slicer.
Selector slicers
Some single-select slicers do not filter data: they switch what the charts show, and one value is always selected.
| Slicer | Report | Switches between |
|---|---|---|
| Show Variance As | Actual and Forecasted Cost vs. Budget | Actual and forecasted variance |
| Scheduled / Actual | Utilization Reports | Scheduled and logged hours |
| Allocation Type | Planning Reports | Hard and hard + soft allocations |
| Group By | Utilization Reports, Planning Reports | Job role, skill and team |
| View Selector | Utilization Reports, Planning Reports | Monthly and weekly view |
| Metric to Show | Profit Forecast | Expected profit in $ and weighted % |
| Time Logged By | Time Logs | Customer, space, portfolio, project and person |
Navigating reports
Most answers are one hover or one right-click away.
| Action | How |
|---|---|
| See a definition or exact value | Hover over a value, a KPI heading or the ⓘ icon |
| Open details for an item | Right-click a bar, a point or a table row and select Drill through > the page name |
| Return from a details page | Click the Back arrow in the top-left corner of the page |
| Enlarge a visual | Hover over the visual, click More options (⋯) > Focus mode |
| See the numbers behind a chart | More options (⋯) > Show as a table |
| Export data | More options (⋯) > Export data; the export respects the current filters |
Notes:
- Details pages: Portfolio & Project Health > Project Health and Risk Assessment > Project Risk Assessment. Right-click a project in any chart or table to open them.
- A details page keeps the filters of the page you came from. If the details look incomplete, check the slicers on the source page.
Troubleshooting
Most questions come down to four checks: the refresh time, the slicers, the item's status in Birdview, and its dates.
The numbers differ from what I see in Birdview
- In a Refresh report, check Last Refresh: changes made after it are not in the report yet.
- Check the slicers and click Reset to default to rule them out.
- Compare like with like: hours of a parent activity include all its sub-activities.
A project or activity is missing
- The project is archived, in a draft status or a template: these are always excluded.
- The report has a fixed time window, for example completed projects in Risk Assessment (see Which items are included).
- The item is outside the selected period or slicer values.
- The activity has no start or end date, so it cannot be placed on a timeline or Gantt chart.
- The item was deleted in Birdview.
Health shows Not Calculated
The project has not started yet (its start date is today or later) or is in a status treated as completed.
Almost every project shows Action Required
Their end dates are in the past. Move the end dates of ongoing projects into the future in Birdview.
The page is blank
In a single-project report, no project is selected. Select one in the Project slicer or click Reset to default.
Utilization is over 100% or capacity is 0
- Over 100%: the planned work exceeds the hours available that period, which often happens in weeks with holidays or vacations.
- Capacity 0: the day is a public holiday or a full-day vacation, or the person's working schedule has 0 hours.
An invoice is missing from the Invoicing Report
Invoices in Draft or Void status are excluded.
Baseline vs Actual shows no variance
No baseline has been captured for the project or the activity yet. Activities without a start date are not shown at all.
The report is slow
Live reports query the database on every click. Narrow the higher-level slicers (for example, Space or Portfolio) before selecting long periods or many projects.
I cannot open the reports, or a report is missing
Ask your administrator to check that your access level has Access to BI Dashboards and that the report is not limited to other access levels.
Can I add our custom fields to a report?
Out-of-the-box reports use standard Birdview fields. Reports with custom fields or your own workflows are built as Custom reports: contact your Customer Success manager for an estimate.
Related articles
The links below might be useful:
Activity health
Trouble and problem indicators
Project financials
Access levels
Company settings — Vacations
Planning — Managing allocations
Planning — Allocated hours calculations
Invoices — Creating an invoice